Good morning all,
I have recently come across to Smartsheet having previously been used to working with Microsoft Project. I have just completed a relatively complicated programme and have just noticed that it only displays one critical path, but won't show two critical paths in parallel. I know it is not a sequencing issue, because if I reduce one path duration by a day, then the other path becomes critical and vice versa. But if I show both paths with the same amount of time, then the programme only selects one path.
Is there a way around this?
I notice a comment from a previous post (copied in below) a couple of years ago saying this should not happen?