Hi!
Working with one of the Smartsheet sprint planning templates and would like to be able to set different working patterns as two parties contributing to the sprint.
i.e. Team 1 work Mon-Friday 8 hour day but Team 2 work everyday except Friday.
Setting the working days in Smartsheet for either Team means that the opposing team is then scheduled (from a resourcing and duration perspective) incorrectly.
Setting a 7 day work week for example within a 14 day sprint with Task XX taking 6x days means that Team 1 are scheduled to work on a Saturday (when they don't work) rather than a Mon-Fri + Mon.
Am I missing something really obvious as a workaround? Should I be approaching this differently?
Many thanks!