Hello,
I have looked around and did not find any responses that directly address my issue. We have a contract that requires monthly reporting. In this contract we are responsible for submitting a monthly report each month on the date of the contract award. I was expecting to be able to simply put a predecessor field with a 1 month lag. I found that this is not possible in Smartsheets. I have been manually setting the dates for these reporting tasks. When a contract award data moves or is delayed all of these tasks have to be manually updated.
Is there any way to put a delay in the predecessor field? I was thinking something in the predecessor field like 34FS + DATE(YEAR([Start Date]3), MONTH([Start Date]3) + 1, DAY([Start Date]3)). Clearly this does not work because it produces a date field. I can't seem to put a function like =DATE(YEAR([Start Date]3), MONTH([Start Date]3) + 1, DAY([Start Date]3)) in the [Start Date]10 field.
The actual program tasking is scheduled with predecessors and works well with days and weeks for durations. It is only the required monthly tasks that are based on contract award that is an issue.
Thanks -Joe.