Start & Finish date cannot be edited with mobile device
We are using sheets with Duration, start date, finish date and Predecessors.
if we use PC to change start date, warning show up "Mannually change start date will remove predecessor", and I can still click ok to do so.
However, I can not do the same in Mobile device unless NO predecessor relationship in the row.
Is that a solution that i can do the same in mobile device (iphone, iPad, Android) as in PC?
Answers
-
Hi @Admin OL
As you have found, it's currently not possible to edit the start date used in Project Settings with predecessor relationships from the mobile app.
Please submit an Enhancement Request when you have a moment!
Thanks,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 67 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives