Free Accounts and the way they can change Task Bars
I am the owner and admin of a 20 people Team. We manage most of our projects on a Gant charted Sheet. I have recently come to realize, that the ones on a free plan are OK to change dates, but are not allowed to pull the task bars with their mouse (except their end date individually) - which is pretty annoying and seems rather as a bug to me.
Anyone else experienced the same?
kind regards,
András ONODI
CEO @ ZOA
Best Answer
-
THIS WAS SOLVED! :)
Thanks Andrée,
The solution was, that the Predecessor Column was locked. Wow. Hope this helps for anyone visiting this thread.
András
Answers
-
Hi András,
Not sure I follow!
It should work. What are the teams permissions?
Can you describe your process in more detail and maybe share the sheet(s)/copies of the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
✅Did my post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Dear Andrée,
Thanks for your prompt reply. I hava attached a small part of our Projects-Sheet as a screencap
. This is one of like 50 projects that we have here. People complaining have their sheets shared as "Editor - cannot share"
Thanks for helping me out.
András ONODI
CEO @ ZOA
-
Happy to help!
Do they get an error message when they try to move it?
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
THIS WAS SOLVED! :)
Thanks Andrée,
The solution was, that the Predecessor Column was locked. Wow. Hope this helps for anyone visiting this thread.
András
-
Happy to help!
Glad we got it working!
✅Remember! Did my post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 67 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives