Hour level of detail
Corentin Dal Farra
✭✭✭✭✭✭
Hello everyone,
Do you know if it is possible in Smartsheet to have a task tracking sheet with tasks that have start hour and finish hour, rather than start date and finish date ?
Thank you and have a great day,
Corentin
Answers
-
It is possible, but time calculations can get a little tricky in Smartsheet. What you cannot do though is have it displayed on the Gantt chart or used as a normal dependency/predecessor.