Task dates
Chichi
✭✭
Hello,
Is it possible for me to create new tasks that has a starting date tied to the end of one task, and a finish date tied to the end of another subsequent task?
Thank you
Answers
-
You can do this using predecessors if you have dependencies turned on. If you do not, you can use cell references in formulas.