I'm trying to trigger the flag in the overdue column if we've missed the proposed response date. My formula is calculating, but it's not turning the flag on. What am I doing wrong?
=IF([PROPOSED RESPONSE DATE]2 < TODAY(), "1")
Try Removing the quotes from around the "1".
=IF([PROPOSED RESPONSE DATE]2 < TODAY(), 1)
Okay, I figured out the flag part. However, now it's immediately flagging if a date hasn't been entered yet. Here's the formula that I'm using. . .
=IF(TODAY() > [PROPOSED RESPONSE DATE]@row, 1, 0)
Please help! Thank you!!!
That's because blank date fields are considered less than any entered date (nothing is less than something kind of thing). We can use an AND statement to include the criteria of it being an actual date.
=IF(AND(ISDATE([PROPOSED RESPONSE DATE]@row), TODAY() > [PROPOSED RESPONSE DATE]@row), 1, 0)
Perfect! Thank you!!
Happy to help! 👍️
Hello! I am attempting to create a dashboard widget that shows me how much budget we are spending in each segment, and in what category. The source sheet contains these columns… "Budget" - text/number column "Category" - dropdown list (restricted to list values only) "Segment" - dropdown list (allows multiple values per…
How can I change the value in one row based off of information in that row and information in a predicessor row
Hi there, I have a project where in the project plan, based on the start date selected for a task, I'd like Smartsheet to reference another sheet (which is the table of Sprint, Start Date, Proposed Completion Date, Sprint Label) and populate the Sprint Column with the correct Sprint Label). So the formular should check…