timeline variance
Is there a way to show a budgeted vs. actual timeline on a Gantt chart without creating Actual and Budget rows? If I go to Project Settings, Dependency Settings, I only see one "Date range display" available.
Answers
-
Hi Mark,
There currently isn't the functionality in Smartsheet to show timeline variance in this way on a Gantt chart. Please submit an Enhancement Request when you have a moment!
In the meantime, you may want to review this other Community post that goes over an alternative way to track this, including a video resource:
https://community.smartsheet.com/discussion/comment/241683#Comment_241683
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 142 Industry Talk
- 473 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives