timeline variance
Is there a way to show a budgeted vs. actual timeline on a Gantt chart without creating Actual and Budget rows? If I go to Project Settings, Dependency Settings, I only see one "Date range display" available.
Answers
-
Hi Mark,
There currently isn't the functionality in Smartsheet to show timeline variance in this way on a Gantt chart. Please submit an Enhancement Request when you have a moment!
In the meantime, you may want to review this other Community post that goes over an alternative way to track this, including a video resource:
https://community.smartsheet.com/discussion/comment/241683#Comment_241683
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 219 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives