Predecessor Plus One Year

I've been using 52 weeks (for example: 17FF + 52w) to give me a 1 year warranty expiration date from the end of the project gantt. It would be nice to have a full year option, like this: 17FF + 1y

Answers

  • Sean Morgan
    Sean Morgan Employee
    edited 05/30/20

    Hello @Ezra

    I love this idea! I can definitely understand the use case scenario for this, especially in project sheets.

    If you have not done so already, please can you raise an Enhancement Request using the quick links under Additional Resources.

    We really appreciate your input, and as we continuously expand our product, I too hope to see this in the future.

    Regards

    Sean