Generate Weekend Dates When Project Settings are Monday - Friday
@Kerlyn Mottershead I moved your question to a separate thread.
Your question:
I have a problem and hope you have a solution.
My project duration days are weekdays only so I set my project settings as such. However, I do have a few tasks that only occur on weekends and my sheet is not calculating that in based on my settings. Do you have a formula that will deliver a date based on a predecessor that is a weekend and ignores the weekday? I hope that made sense.
Kay!
Answers
-
@Kerlyn Mottershead Do you have dependencies enabled on your sheet?
If so, you will need to either adjust the working days in your project settings, turn them off and replicate how they work using formulas, or use a second date type column that would house a formula, but this second column would not be usable in the dependency settings.
-
Thanks! I will try to replicate the settings using a formula.
-
Happy to help! 👍️
Feel free to let me know if you would like some assistance on getting those put together.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!