I've searched a bit and there's been some questions that's the same but so far none of them helped me.
We create a project with planned start and end dates (some call these baseline dates) and then as we go through the project the dates changes in order to see when we will actually deliver the project. The dates we change is the Actual Start and End dates.
I'm looking for a way to easily compare these dates. So Task 1 should have taken 5 days but it took 8 days and this pushed out Task 2 by 3 days already. But now task 2 took 2 days longer so Task 3 is now 10 days in a delay. We want to show this to the stakeholders in order for them to take more accountability on their side about delays in the project. Is something like this possible in Smartsheets?