How can I set-up my Gantt sheet, to plan from end date to starting date?
Hi everyone,
I'm trying to make a planing scheduel starting from my ending due date. I need it to calculate automaticly my starting date. Can anyone help me?
Answers
-
If you're working with a Project Sheet with Project Settings enabled, you will first want to fill out the Duration column for how many days the task will take. Then, once you have that number, fill in the Finish date column, which will automatically populate the Start date!
You can learn more about Start and Finish dates with Project Settings in the Help Center (see here).
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.2K Get Help
- 360 Global Discussions
- 199 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 444 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!