How can I set-up my Gantt sheet, to plan from end date to starting date?
Hi everyone,
I'm trying to make a planing scheduel starting from my ending due date. I need it to calculate automaticly my starting date. Can anyone help me?
Answers
-
If you're working with a Project Sheet with Project Settings enabled, you will first want to fill out the Duration column for how many days the task will take. Then, once you have that number, fill in the Finish date column, which will automatically populate the Start date!
You can learn more about Start and Finish dates with Project Settings in the Help Center (see here).
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.3K Get Help
- 445 Global Discussions
- 144 Industry Talk
- 477 Announcements
- 5K Ideas & Feature Requests
- 85 Brandfolder
- 151 Just for fun
- 72 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 302 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!