How can I set-up my Gantt sheet, to plan from end date to starting date?

Hi everyone,

I'm trying to make a planing scheduel starting from my ending due date. I need it to calculate automaticly my starting date. Can anyone help me?

Answers

  • Genevieve P.
    Genevieve P. Employee
    edited 07/02/20

    Hi @Compte Général

    If you're working with a Project Sheet with Project Settings enabled, you will first want to fill out the Duration column for how many days the task will take. Then, once you have that number, fill in the Finish date column, which will automatically populate the Start date!

    You can learn more about Start and Finish dates with Project Settings in the Help Center (see here).

    Cheers,

    Genevieve

    Need more help? 👀 | Help and Learning Center

    こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!