Adding Time to a Project Plan via Forms
I have a normal/typical/simple project plan sheet: task, duration, assigned to. In lieu of having the Proj Mgr ask the engineer, how much he accomplished on the task and then putting that time into the project plan manually, is there a way that I can give a form to the engineer, that includes a dropdown that reads the appropriate tasks which he is assigned to, and then have that time get put directly into the project plan?
Best Answer
-
If this is for an existing row of data you will need to use an Update Request.
See https://help.smartsheet.com/learning-track/smartsheet-intermediate/update-requests
School of Sheets (Smartsheet Partner)
If my answer helped please accept and react w/💡Insightful, ⬆️ Vote Up, ❤️Awesome!
Answers
-
If this is for an existing row of data you will need to use an Update Request.
See https://help.smartsheet.com/learning-track/smartsheet-intermediate/update-requests
School of Sheets (Smartsheet Partner)
If my answer helped please accept and react w/💡Insightful, ⬆️ Vote Up, ❤️Awesome!
-
Yes, this is a perfect answer to what I am trying to accomplish. Thanks very much!!!!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 145 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!