Resources view

Hi,

Is it normal that, in resources view, they still count task who are 100% achieved? My ressource seems overloaded but in reality, some task are completed.

How can I avoid that?

Thanks

Best Answer

Answers

  • Dave Hymers
    edited 03/03/21

    Hi Genevieve,

    I am frustrated with this same issue, I realize that adjusting dates post completion may be simple for some users, and also accurate task hour assignment is important. Having completed blue dotted tasks not appear in resource view (or be tagged in a different color) would be very helpful in this task and also quickly being able to re-assign resources that are ahead of task.

    I have submitted a product enhancement request.


    Thanks

    Dave

  • Hi Dave,

    Thanks for submitting the enhancement request, I know our Product Team always appreciates receiving feedback and reads through each suggestion.

    Need more help? 👀 | Help and Learning Center

    こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions