Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Dependencies and Predecessors
I am brand new to using Smartsheets and need help on creating multiple date dependencies. I want to track a myriad of tasks over time, ultimately based on a final event date. Each task has a different due date in realtionship to the final event date, and would thus have a different start date. The tracking document also has predecessors. How do I properly set up the dependencies to accomplish this?
Comments
-
Jenny,
First, make sure you have two Date type columns in your sheet.
Go to the Gantt view and find the little gear symbol - that is the Project Settings.
In Project Settings, enable Dependencies.
This will add the Predecessor column if it doesn't already exist.
Your dependencies are built in the Predecessors column.
See this article for more:
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives