Calculate number of days a task is later than forecast end date

Dan Harris
✭✭✭✭✭
Hi,
Can somebody help?
I need to add a column that calculates how many days late tasks less than 100% complete are compared to today see below example, basically need a formula that calculates the 'working days late' column.
Thanks
forecast end date % Complete working days late (based on todays date)
3/8/20 99% 2
Tags:
Answers
-
Hi Dan,
Try this formula in your [Complete working days late] column,
=IF([date %]@row < 1, TODAY() - [forecast end]@row, "-")
Hope this helps,
Mathieu | Workflow Consultant
info@evolytion.com
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.9K Get Help
- 441 Global Discussions
- 153 Industry Talk
- 501 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 79 Community Job Board
- 511 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!