Report in Gantt View
Hi,
When i report the schedule using Gantt View, the progress bar does not show.
Please clarify. What could be the reason>
Answers
-
Does the progress bar show on your source Sheet(s)? You will need to have project settings enabled and % complete column selected for it to show.
See this video for information on how to add this to a Sheet.
👨🏼💻 Dan Palenchar | School of Sheets Solutions Consulting | Smartsheet Aligned Gold Partner
If this helped, help me & the SSC by accepting and reacting w/ 💡insightful, ⬆️ Vote Up, and/or ❤️Awesome!
- 🆘 Smartsheet Consulting Inquiries: schoolofsheets.com/workwithus
- ▶️ Smartsheet Tutorial Videos: schoolofsheets.com/youtube
PS - If you have a follow up response tag me @SoS | Dan Palenchar so I get notified of your reply!
-
Thanks Dan.
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives