Report in Gantt View

Sai Ramanan
✭✭
Hi,
When i report the schedule using Gantt View, the progress bar does not show.
Please clarify. What could be the reason>
Answers
-
Does the progress bar show on your source Sheet(s)? You will need to have project settings enabled and % complete column selected for it to show.
See this video for information on how to add this to a Sheet.
School of Sheets (Smartsheet Partner)
If my answer helped please accept and react w/💡Insightful, ⬆️ Vote Up, ❤️Awesome!
-
Thanks Dan.