Gantt Chart Markers
Is there a way to create a marker on a gantt chart?
For example, the entire task timeline is 11/1/20 - 12/31/20 and I want to add in a midway point marker such as a dot with halfway there within that timeline.
Best Answer
-
Sort of ... create a task in between the two tasks where you want the marker and give it a duration of zero and then make it dependent on the first part and make the second part dependent on it.
Here's what it might look like:
I hope this helps.
Cheers,
Ramzi
Ramzi Khuri - Principal Consultant @ Cedar Tree Consulting (www.cedartreeconsulting.com)
Feel free to email me: ramzi@cedartreeconsulting.com
💡 If this post helped you out, please help the Community by marking it as the accepted answer/helpful.
Answers
-
Sort of ... create a task in between the two tasks where you want the marker and give it a duration of zero and then make it dependent on the first part and make the second part dependent on it.
Here's what it might look like:
I hope this helps.
Cheers,
Ramzi
Ramzi Khuri - Principal Consultant @ Cedar Tree Consulting (www.cedartreeconsulting.com)
Feel free to email me: ramzi@cedartreeconsulting.com
💡 If this post helped you out, please help the Community by marking it as the accepted answer/helpful.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!