How can I create a calendar in Smartsheet so that it allows a GANTT view?
Answers
-
Hi @Tracey Nelson,
Here's a link to some Smartsheet Instructions: https://help.smartsheet.com/articles/765675-work-with-gantt-chart
Essentially you must have at least 2 date columns to use the Gantt View. Once in that view you can define which columns you want to be the start date and end date.
Hope this helps!