Dependancy
Jen Payne
✭✭
Everytime I am attempting to change my predeccssors type (Finish -Start/finish-finsh etc) it tells me there is an error. "Circular Dependency". Can someone please give me a sample of how to setup?
Thanks
Comments
-
The value in the predecessor column is the row(s) of the task(s) that will preceed, meaning you cannot put a predecessor of 1 in row 1. See the help article here: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Here is a sample
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 351 Global Discussions
- 198 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 443 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 36 Webinars
- 7.3K Forum Archives