Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Dependancy
Jen Payne
✭✭
Everytime I am attempting to change my predeccssors type (Finish -Start/finish-finsh etc) it tells me there is an error. "Circular Dependency". Can someone please give me a sample of how to setup?
Thanks
Comments
-
The value in the predecessor column is the row(s) of the task(s) that will preceed, meaning you cannot put a predecessor of 1 in row 1. See the help article here: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Here is a sample
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives