Make on weekend as working days
Roberto Herrero
âś
I need to make one weekend as working days in my project. I don't want to create a parent task with sub tasks. I want to force the weekend to be a working days.
I appreciate your help
Rob
Tags:
Answers
-
Hi Rob,
If you just want to include one weekend from your entire project (versus always making Saturdays or Sundays working days), then you can use elapsed time in your project.
In your Duration column, add an e before your number of days for that row. Ex. e7. This would count all 7 days as "working days" without skipping over weekends. (See here for more information.)
Let me know if this works for you!
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.4K Get Help
- 364 Global Discussions
- 200 Industry Talk
- 429 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 446 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 35 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!