Hi there,
I have tasks with targeted start and targeted finish dates, all with appropriate predecessors with or without lag, as well as durations.
Is there a way for the targeted completion date to remain as a target until the actual completion date is entered?
For example, someone signs a letter of intent 100 days after our typical timeframe for signing an LOI. I adjusted the lag, but curious if there was an easier, less manual way of updating the targeted date so all tasks following this one will update appropriately.
Also, how does everyone handle milestone tasks that have zero duration so it is called out as a milestone? Do you have the same task listed twice, one with 0 duration and one with the actual duration? Or do you use lag on tasks that are dependent on it?
Any insight is much appreciated.
Bri