I've been working in a CPM schedule. The original showed a 141 day duration, starting 12/12 and ending 05/04. I'm updating some of the relationships as I had to rearrange the work pattern a bit, now my schedule shows 144 days, starting 12/12 and ending 6/29. Does anyone have an answer as to how I gained only 3 days duration yet two full months were tacked onto my end date? I have a feeling it's the way Smartsheet defines duration... but I would thing duration is linked to the days between the start and end of a project.
Insight would be appreciated.