Milestones
Hi there!
From what I understand with smartsheets, a milestone must have a start date and 0 duration.
In the attached example, the arrowed tasks take a number of days to complete. However, I want to highlight these tasks as a milestone but also display the time it takes to complete them.
How would I go about doing this?
Thanks!
Best Answer
-
Hi @smartsheets1 ,
I don't think you can create a multi-day milestone. You can have it fill 1 day by using a duration of ~0. See article below.
You can also add a milestone task (start date with 0 duration) after your highlighted tasks. If you make your tasks presecessors the milestone will move as the schedule changes.
Maybe someone else has a better solution.
Mark
I'm grateful for your "Vote Up" or "Insightful". Thank you for contributing to the Community.
Answers
-
Hi @smartsheets1 ,
I don't think you can create a multi-day milestone. You can have it fill 1 day by using a duration of ~0. See article below.
You can also add a milestone task (start date with 0 duration) after your highlighted tasks. If you make your tasks presecessors the milestone will move as the schedule changes.
Maybe someone else has a better solution.
Mark
I'm grateful for your "Vote Up" or "Insightful". Thank you for contributing to the Community.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives