Task duration as a function of the task Allocated %
Hello!,
Can task duration be calculated as a function of the allocation percentage?
If one person is allocated 100% for one week then being allocated at 50% the task should take two weeks, etc.
Another case may also be useful. If one person is allocated 100% for three weeks then allocating 300% the task should take one week, etc. This option allows a quick What If resource allocation answer.
I'd appreciate suggestions on how to do this.
Thank you,
Michael
Answers
-
Hi @Michael Wilson,
I really like this idea of having a link between Duration values and Allocation percentages but without being able to create formulas in Dependency Columns, I'm not sure of the best way to go about this type of setup. I highly recommend Submitting a Product Enhancement Request to see about implementing this type of connection in a future release or for allowing formulas in project columns on dependency-enabled sheets.
Thanks,
Ben
-
Hi @Ben G ,
I am glad you like this idea.
Thanks for your support.
Thanks also for your suggestion of submitting a product enhancement. It seems, however, that this capability has been missing for some time.
Thanks again,
Michael.
-
What's the work around? I have seem posts concerning this issue on the forums that go back to 2015.
-
I saw the same 2015 discussion with no apparent resolution.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 58 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives