Helper Column to compare Dates

Options

Hi,

I am working to figure out a way to compare actual project dates to planned project dates. I linked the actual project dates from our active program view.

If the Actual End date does not pass the Planned End date I want the "State" Column to be green.

If the Actual End date is past the Planned date but within 21 days, I want the "State" Column to be yellow.

If the Actual End date is more than 21 days past the planned date then I want the "State" column to be red.

Can I do this with a formula in the state column or do a helper column? If so, what would the formula be?

Thank you!

Best Answer

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!