Weeks to Project Due
Hi All,
I am looking for a very simple formula to help me return the following:
The product due date is 10/17/21, week 0, and I would like to create a formula to tell me what working week we are currently in today.
I am able
Any help is greatly appreciated
Best Answer
-
Can you work out the number of days between the Product Due date and Today and divide the answer by 7? (take the Integer result) - would that work?
=INT(([Product Due Date]@row - Today())/7)
Any good?
Or if you wanted the week numbers to show in negative then swap the subtraction around like this:
Answers
-
Can you work out the number of days between the Product Due date and Today and divide the answer by 7? (take the Integer result) - would that work?
=INT(([Product Due Date]@row - Today())/7)
Any good?
Or if you wanted the week numbers to show in negative then swap the subtraction around like this:
-
Perfection! Thank you so much!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!