Some milestone icon not display in Gantt View
Hi,
I created a project plan with a gantt view with sign-off milestone and I wanted to have the diamond icon show for all milestone. Some of the milestone have a diamond icon defaulted but some of the milestone is not link with the icon. I am not able to find any option to edit the icon.
Refer to the screenshot, the go live readiness and warantty completion sign off to show diamond icon. I tried in both project plan and report gantt view but not successful.
Kindly advise. Thanks
Best Answer
-
Hi @Angeline Lai
Hope you are fine, as i see in your chart you have a duration for sign off milestone, when you have a duration for the activity you will not see the diamond icon.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Answers
-
Hi @Angeline Lai
Hope you are fine, as i see in your chart you have a duration for sign off milestone, when you have a duration for the activity you will not see the diamond icon.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
Thanks Bassam! Have made the changes and the milestone shows. :)
-
You are welcome
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives