Some milestone icon not display in Gantt View
Hi,
I created a project plan with a gantt view with sign-off milestone and I wanted to have the diamond icon show for all milestone. Some of the milestone have a diamond icon defaulted but some of the milestone is not link with the icon. I am not able to find any option to edit the icon.
Refer to the screenshot, the go live readiness and warantty completion sign off to show diamond icon. I tried in both project plan and report gantt view but not successful.
Kindly advise. Thanks
Best Answer
-
Hi @Angeline Lai
Hope you are fine, as i see in your chart you have a duration for sign off milestone, when you have a duration for the activity you will not see the diamond icon.
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Answers
-
Hi @Angeline Lai
Hope you are fine, as i see in your chart you have a duration for sign off milestone, when you have a duration for the activity you will not see the diamond icon.
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
Thanks Bassam! Have made the changes and the milestone shows. :)
-
You are welcome
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"