Gantt Chart - Percentage Complete
Hi,
I'm new in Smartsheet coming from the MS Project world.
I'm trying to include the % of task completion in a gantt chart.
I'm filling in the % complete column but nothing appears on the gannt chart (contrary to what is described in https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors)
I noticed that in Project Settings, the pull down menu for '% Complete Column' does not include the '% Complete' option (contrary to what is again ilustrated in https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors)
Have I messed with any of the settings?
Thank you,
Harry
Answers
-
I hope you're well and safe!
Can you maybe share some screenshots of your settings and sheet? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@workbold.com)
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Did you create the percentage complete column yourself?
If so, is it formatted as a % column using the % button in the toolbar?
-
Please find attached screenshots of:
- the '% complete' column and its settings (it is formatted as % - the button on the toolbar is pressed)
- the project settings - showing the available options in the pul down mnu
-
Strange!
I'd be happy to take a quick look.
Can you maybe share the sheet(s)/copies of the sheet(s)? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@workbold.com)
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hello @Harry Karandeinos , were you ever able to accomplish this? I'd also like to add the percentage completed on the Gantt chart.
Thanks,
Adam
-
Hi
I am curious to the same. The % complete is not showing on my Gantt either but would like it to do so.
-
Here is a quick video demonstrating the creation of the percent complete column based on a brand new sheet and converting it to GANNT. You have to remember that when a column is tied to percentages it works of part of a whole number... .1 is 10%.
-
-
@Mike Wilday your video helped me thank you!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 58 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!