Is it possible to add the ability to change the parent row color settings, especially as relates to task bar color in gantt view?
This discussion has been merged.
Hello everyone, I hope you're doing well. I'm new to SmartSheet and currently working on my initial projects and automations. I have a project group and would like to create a report in the project management office that allows me to identify all the collaborators involved in each project and in which months they will be…
Hi all, I like the gantt view in SS. However, I am not able to move left and right. Any idea what's happening?
In a Report, I see a vertical line for "today's date" on the Gantt Chart. However, when the report is dropped onto a Dashboard, the vertical line is not displayed. Any suggestions?
I want to calculate the working days from the start date. However, we have Sat as a working day which I have configured in the Gantt setting. (So we have 6 working days). When I use the formula WORKDAY ([Start Date],38), from 3-Mar-2024, I get the output as 16-Apr-2024 - which is correct. 3-Mar-2024 being Sunday. When I…
Hi, I'm new in Smartsheet coming from the MS Project world. I'm trying to include the % of task completion in a gantt chart. I'm filling in the % complete column but nothing appears on the gannt chart (contrary to what is described in…
Current status: I've successfully generated a "Successors" column, listing direct successors of each row, using the following formula: =JOIN(SUCCESSORS([Task Name]@row), ",") Current roadblock: My "successors" column only shows direct successors. I'm looking to create a column that lists ALL successors, all the way up the…
WHY IS THIS USEFUL? This updated function would allow us to filter the spreadsheet for only the driving path to a particular row#. This would be similar to a filter for critical path, but enable much more flexibility. Current status: I've successfully generated a "Successors" column, listing direct successors of each row,…