Calculating NETWORKDAYS for a 6 day week
Hello,
I need a formula to calculate days gained/lost on a project which has 6 working days per week.
Is there a way to calculate NETWORKDAYS for a 6 day week in Smartsheet, similar to NETWORKDAYS.INTL function in Excel?
Or is there an alternative way to calculate days gained/lost?
Thank you.
Answers
-
Hi @Natalia O'Grady
Hope you are fine, the following article will give you full details about NETWORKDAYS Function in Smartsheet, and for six working days in the week you can configure smartsheet to use this rule from the admin center the following article will help you Define Working Days, Non-working Days, and Holidays on a Project Sheet
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.4K Get Help
- 364 Global Discussions
- 202 Industry Talk
- 430 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 446 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 35 Webinars
- 7.3K Forum Archives