Gantt view not showing critical path in red
I recall this may be an issue with indentation but can't find the information now.
I would like to use my sheet as both a master task tracker and a section for schedule. When I click on the critical path icon in gantt view I don't see the content highlighted in red. Dependencies are set and such already.
Answers
-
Hello @beatea ,
Are you able to share a screenshot of the issue? (Please ensure you hide any sensitive data)
In the meantime, you may wish to view the following article to determine the path thats showing currently: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
Kindest Regards
Sean
-
Hi @beatea
Hope you are fine, please check the following article to understand all the details about showing the critical path Track the Critical Path in a Project also please note that :
1- you must check that no open ends for the relationship between activities.
2-you must check the lag between the activities and the total float.
3- you must check the relationship type ( FS-FF-SF-SS) between activities and if it's in the correct logic.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
I have a follow up question - I have a schedule with links from other sheets where I'd like to see the CP. If I add processors to the linked cells in the CP sheet, the dates change.
Two questions
- Will having linked cells prevent a CP from showing up?
- Is there a way to find out what's blocking the CP from looking at the gantt or some other method?
Thanks
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives