I was wondering if automation can be set up to move rows to another sheet at a specific time of the day rather than manually having to change something to make this move happen?
Best Answer
-
You would set your trigger to run based on a date. Click on "Run Once" and select "Custom". There you can change it to daily at a specific time (on the hour only).
Answers
-
You would set your trigger to run based on a date. Click on "Run Once" and select "Custom". There you can change it to daily at a specific time (on the hour only).