Is it better to have projects in their own workspaces or folders?
Hello! I'm seeking advice from experienced users. We will have a master sheet with key information from all of our projects stored for tracking/reporting. However, for all the projects (and considering that we will have active and closed projects), is it better to create a separate workspace for each project or folder?
Thank you!
Best Answer
-
Hi @Teresa Suranyi .
We run many projects, each residing within their own Workspace. A team of people then only have access to those Workspaces that we grant them. As an administrator, I have access to all Workspaces, which can be cumbersome.
If you have a Master Sheet that sits outside of all your Project Workspaces, consider how it will perform when Workspaces are Backed-up / Deleted. You may have to manually link reports/sheets to your Master as new Workspaces are created.
Answers
-
I hope you're well and safe!
It depends.
- How many projects?
- Who should have access?
- What is included with each project?
Can you describe your process in more detail and maybe share the sheet(s)/copies of the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@workbold.com)
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi, Andrée,
Thank you for the questions. Here are my answers:
- This will be our ongoing project tracking, so right now will be around 50, but obviously in a few years, a few hundred.
- Each project team will have access to their project information (either via a folder or workspace depending on what we land on), while the PMO will have access to all projects.
- Each project will have the standard project charter, RAID log, workplan, associated deliverables, etc. attached.
- Certain data points will be automated to be pulled into a master project tracking database.
Thanks!
-
Happy to help!
Sharing is much simpler with Workspaces, and you could have them by project or by the team.
Have you looked at the premium add-on, Control Center?
It's fantastic, and with it, most parts can be automated.
Let me know if you want to explore it and need more information.
What do you think?
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi, Andrée,
Thank you for the offer. At this point, as we are just starting out, we see this as manageable. We will see in the future.
T
-
You're more than welcome!
Yes, that makes sense, but I mentioned it now because if it's interesting, it might be better to implement it now when you set everything up. If you do it later, when you already have many projects going, it will take some time to migrate that information.
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi @Teresa Suranyi .
We run many projects, each residing within their own Workspace. A team of people then only have access to those Workspaces that we grant them. As an administrator, I have access to all Workspaces, which can be cumbersome.
If you have a Master Sheet that sits outside of all your Project Workspaces, consider how it will perform when Workspaces are Backed-up / Deleted. You may have to manually link reports/sheets to your Master as new Workspaces are created.
-
Hi, @Richard Heath.
What do you do when a project is completed? We would want to somehow remove the project workspace from the list of active projects. I had thought of creating a new "Closed Projects" workspace where all the old projects would go; however, because we have different teams accessing the projects, I would then have to manually move all the contents from the workspaces into new folders in the "Closed Projects" workspace and grant permissions to new folders - seems like a lot of work. Alternatively, we thought of a simple "ZZ" addition to the front of the workspace title, which would at least move them down to the bottom of the list. Interested in hearing what others are doing.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives