I want to create a formula that changes the Progress bar to full when the Status column is changed to Complete. I don't want a formula for any of the other Status options.
Thanks in advance.
Best Answer
-
I hope you're well and safe!
Try something like this.
=IF(Status@row = "Complete"; "Full")
Depending on your country/region, you'll need to exchange the comma to a period and the semi-colon to a comma.
Did that work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Answers
-
I hope you're well and safe!
Try something like this.
=IF(Status@row = "Complete"; "Full")
Depending on your country/region, you'll need to exchange the comma to a period and the semi-colon to a comma.
Did that work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi and thank you for responding.
Formula is perfect, I was trying something very similar with no luck.
Slight issue, I've made it a column formula which has changed all of the other progress bars in the column. How can I make it so it only effects when an item is complete? Or should I use a formula for all of the progress bar options (Employ, Quarter, Full and Three Quarter).
Thanks,
Hannah
-
I was searching for something else and came across this post - did you figure out how to build the rest of the formula?
You're correct, you would need to create a rule for each of the levels of progress for the bar, identifying when it should be Full, Empty, etc. This would be a nested IF statement, similar to how you'd change a status ball colour.
If you still need help, it would be useful to know what the criteria is for each individual bar option.
Thanks!
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 371 Global Discussions
- 203 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 448 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!