Parent and child rows
Hello,
I need assistance with managing parent and child rows in Smartsheet. How can I display a milestone as completed once all of its child rows are marked as 100% complete? For example, if I complete all the rows under Milestone 5, how can I set Milestone 5 to show 100%? Thank you in advance for your help.
Best Answer
-
If you set your % Complete column as the column to use in the project settings, the parent row should be updated automatically.
Answers
-
You can use the "parent rollup functionality."
Please check the similar post for this discussion.
Please make sure you set the % Complete column options.
-
If you set your % Complete column as the column to use in the project settings, the parent row should be updated automatically.
-
Thank, you @Paul Newcome
-
Happy to help. 👍️
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 69 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives