90 Days Prior to a Target Date Formula
Hi There,
I've reviewed the forms and found a formula that seems to work for everyone but me:
=[Target Submit for Comment Date]@row - 90
I get Invalid Column Value error.
I just need to calculate 90 days before a specific date - how would I go about doing that?
Thanks!
Best Answers
-
If you go to "Column Properties" of the column where your formula is and change the type to "Date", this formula should work just fine (it did for me a few minutes ago).
-
Here is a screen capture of the process.
Answers
-
If you go to "Column Properties" of the column where your formula is and change the type to "Date", this formula should work just fine (it did for me a few minutes ago).
-
Here is a screen capture of the process.
-
THANK YOU!!
-
@Blake Neyland , how about if I wanted to use the above formula but not for the entire column just the ones that are marked as "New" in the another column?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!