=IF([Deployed Y/N]@row = "Y"; 1)
Depending on your country/region, you'll need to exchange the comma to a period and the semi-colon to a comma.
Did that work/help?
I hope that helps!
Be safe and have a fantastic day!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please help the Community by marking it as the accepted answer/helpful. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:[email protected] | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
@Andrée Starå Thanks yes it worked when I replaced the semi colon with a comma.
Have another query....
I want the "DRP Install" column to pull the date in the "TA Go Live" when the "Delivery Y/N" Column has a "Y" any ideas on a formula that could work?
Thanks
-
-
Happy to help!
Try something like this.
=IF([Deployed Y/N]@row = "Y", [TA Go Live]@row)
Did that work?
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:[email protected] | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
Check out the Formula Handbook template!