Number of day to complete less weekends
I am currently using the formula below to calculate the number of days to complete a task. Is there a way to exclude weekends. (option 1), and possibly a custom list of holidays (option 2)?
=[Resolved Date]@row - [Created Date]@row
Tags:
Answers
-
Use NETWORKDAYS formula to exclude weekend and custom list of holidays.