Count Days in between, without weekends / day of
Hello,
I am trying to create a formula where "Aging of Orders" represents the days between "Actual delivery date" and "Requested Due Date", not including weekends or the "day of". Example - Line 1 I would consider 2 days late, not 3. Due: 1/14/21 Delivered: 1/18/21.
I appreciate any help!
Answers
-
Hi @Elaine Mullis
Hope you are fine, please try the following formula:
=NETWORKDAY([Actual Delivery Date]@row, [Request Due Date]@row)
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!