Count Days in between, without weekends / day of

Hello,

I am trying to create a formula where "Aging of Orders" represents the days between "Actual delivery date" and "Requested Due Date", not including weekends or the "day of". Example - Line 1 I would consider 2 days late, not 3. Due: 1/14/21 Delivered: 1/18/21.


I appreciate any help!

Answers

  • Bassam Khalil
    Bassam Khalil ✭✭✭✭✭✭

    Hi @Elaine Mullis

    Hope you are fine, please try the following formula:

    =NETWORKDAY([Actual Delivery Date]@row, [Request Due Date]@row)

    PMP Certified

    bassam.khalil2009@gmail.com

    β˜‘οΈ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!