Hi All,
I am trying to find a simple formula that allows me to add months onto a date to get an automated due date.
So date completed column plus whatever figure i put in months column ( up to 12 months) and then this to populate in the Due date column.
Tags:
Answers
-
=IFERROR(DATE(YEAR([Date Completed]@row), MONTH([Date Completed]@row) + Months@row, DAY([Date Completed]@row)), DATE(YEAR([Date Completed]@row) + 1, MONTH([Date Completed]@row) - Months@row, DAY([Date Completed]@row)))
-
Hi James, this only works up to four months and everything else including 12 months is not correct
-
Hi @KatieB - Have you tried converting it to days?
[Date Completed]@row + 90
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!