Start and Finish Dates
Hello,
I have the following columns:
1) Planned Start Date and Planned Finish Date
- the above two columns are defined with predecessors and durations which link the dates
2) Actual Start Date and Actual Finish Date
- I'd like to create predecessors and durations with the above Actual Dates. How do I do that?
It seems the Project Settings only allow me to select one set of Start/Finish date columns. Can I have multiple start/finish date columns?
Thanks!
AE
Best Answer
-
Hi @Amy Evans
You're correct, a Project Sheet in Smartsheet can only associate one set of Start / End date columns with Predecessors and Duration.
One solution would be to write formulas in other columns to mimic certain functionalities, if needed. (Such as using a NETWORKDAYS function to calculate the number of working days between two dates, for a "Duration x2" column).
However, I would suggest having your Actual Start Date and Actual Finish Date columns be the ones set in your Project Settings, then set a Baseline in your sheet (automatically creating the Planned Start and Finish). This will then calculate the variance, and show a thin grey bar on the Gantt chart for your review. See this webinar: Keep Your Projects on Track with Baselines and this Help Article: Set Baselines on a Project Sheet
Cheers!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
Hi @Amy Evans
You're correct, a Project Sheet in Smartsheet can only associate one set of Start / End date columns with Predecessors and Duration.
One solution would be to write formulas in other columns to mimic certain functionalities, if needed. (Such as using a NETWORKDAYS function to calculate the number of working days between two dates, for a "Duration x2" column).
However, I would suggest having your Actual Start Date and Actual Finish Date columns be the ones set in your Project Settings, then set a Baseline in your sheet (automatically creating the Planned Start and Finish). This will then calculate the variance, and show a thin grey bar on the Gantt chart for your review. See this webinar: Keep Your Projects on Track with Baselines and this Help Article: Set Baselines on a Project Sheet
Cheers!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
Thank you Genevieve.
Amy
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives