Text in Gantt chart
How do I change the properties so that the type only shows on the row, and not the gantt chart?
Best Answers
-
Hi @StaceyZ
If you are referring to the task label in the Gantt chart, then you can change what column is used for this text (or remove the text all together) in the Project Settings window, under "Timeline Display" and then "Display label for":
See: Create and Work With a Gantt Chart
Let me know if this is what you were looking to do!
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
-
Thank you Genevieve! Yes, that's exactly what i was looking for. Do you know if you can place markers in the gantt chart, like triangles or circles to mark a specific timepoint?
-
Hi @StaceyZ
You can create a diamond in the Gantt view by entering a task @Stacee Franewith the Duration of 0. This marks the task as a "milestone", will this work for you?
See: Create a Milestone to Mark a Significant Event in Your Project
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Answers
-
Hi @StaceyZ
If you are referring to the task label in the Gantt chart, then you can change what column is used for this text (or remove the text all together) in the Project Settings window, under "Timeline Display" and then "Display label for":
See: Create and Work With a Gantt Chart
Let me know if this is what you were looking to do!
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
-
Thank you Genevieve! Yes, that's exactly what i was looking for. Do you know if you can place markers in the gantt chart, like triangles or circles to mark a specific timepoint?
-
Hi @StaceyZ
You can create a diamond in the Gantt view by entering a task @Stacee Franewith the Duration of 0. This marks the task as a "milestone", will this work for you?
See: Create a Milestone to Mark a Significant Event in Your Project
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
-
Yes! this answers my question! I need to look into some more training! Thanks!
Stacey
-
No problem at all! 🙂
You may find this webinar on Project Management helpful.
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
-
A shame that we cannot add text on the left side of the bar, like in MS Project. I don't think this would be difficult to implement, but add a ton of value. Indeed in some views the top header of the timeline is very broad (Q3 2022) so it is useful to have the end date for example, as well as the task description. I already put in a request to Smartsheet.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 85 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives