Driving path connectors dont show

Hi,

I have created a gantt chart with dependencies but the connectors (showing the dependcies) between the tasks do not appear on the gantt chart

Answers

  • Hi @Harry Karandeinos

    Are you looking at the source sheet or a Report? Reports won't show the driving path as the Report could be formed from multiple sheets.

    If you're talking about the sheet, can you post a screen capture of what you're seeing, with the Predecessor column showing and the lack of connector in the Gantt?

    Thanks!

    Genevieve