How to set a hard deadline and work backwards in Gantt chart
Hello,
I am trying to set a hard dare deadline and estimate how long before I need to have all the steps ready , found the hard deadline template but I don't have any luck using it.
how can I create backward dependences?
thanks
Answers
-
Hi @Irene C,
When you set up your predecessors, you can use FS for Finish-to-Start, or SS for Start-to-Start. If you use the deadline row as your dependency, you can work backward from there.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Holly Conrad Smith
Director of Technology & Innovation 💡 at Streamline
CliftonStrengths Top 5: Deliberative, Restorative, Achiever, Consistency, Harmony
-
@hollyconradsmith Thank you for this tip. It helped out quite a bit
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives