How to set a hard deadline and work backwards in Gantt chart
Hello,
I am trying to set a hard dare deadline and estimate how long before I need to have all the steps ready , found the hard deadline template but I don't have any luck using it.
how can I create backward dependences?
thanks
Answers
-
Hi @Irene C,
When you set up your predecessors, you can use FS for Finish-to-Start, or SS for Start-to-Start. If you use the deadline row as your dependency, you can work backward from there.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Holly Conrad Smith
Director of Technology & Innovation 💡 at Streamline
CliftonStrengths Top 5: Deliberative, Restorative, Achiever, Consistency, Harmony
-
@hollyconradsmith Thank you for this tip. It helped out quite a bit
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 396 Global Discussions
- 213 Industry Talk
- 448 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 133 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives