RYG Formula For Plan Vs Actual % Complete
Smartsheet Community:
I tried tweaking a Similar Formula but was Unable to get the Result I desired. Here is what I am looking to Do:
Red:
If the Difference is More Than 10% Between:
% Complete (Actual) And % Complete (Plan)
Yellow:
If the Difference is Less Than 10% Between:
% Complete (Actual) And % Complete (Plan)
Green:
If % Complete (Actual) And % Complete (Plan) Are Equal OR If % Complete (Actual) is Greater than If % Complete (Plan)
Grey:
% Complete (Actual) And % Complete (Plan) Equal 0
Thanks
Answers
-
Assuming that your RYG is related to Task Health in a schedule, then it’s normally based not only on % Complete, but also on TODAY() compared with the planned finish date for the activity. The plan is that every Task is 100% complete, therefore you need second criteria to determine RYG.
For example, you could check if the finish date is within x days in the past or future to determine if it’s close to finishing or late. A Task that is 50% complete and within 1-2 days of the planned finish date might be Yellow, or if past the planes date it would Red.
-
OK! Do you already have such a Formula? If so, I can Modify that Formula to meet my Need.
-
Here is the Formula I Created by Unsuccessful:
=IF([% Complete (Actual)]@row = 1, "Green", IF(AND([% Complete (Actual)]@row, [% Complete (Plan)]@row = 0 "Gray", IF(TODAY() > [Finish Date (Plan)]@row, "Red", IF(TODAY(10) >= [Finish Date (Plan)]@row, IF([% Complete (Actual)]@row < 0.75, "Yellow", "Green"))))
-
hi Anthony,
Could you please share with me your formula for "Planned % Complete"?
And did you also find out the indicators' formulate based on your criteria above?
Highly appreciated.
-
% Complete (Plan) Formula: Parent
=IFERROR(ROUND(AVGW(CHILDREN([% Complete (Plan)]@row), CHILDREN([Duration (Actual)]@row)), 2), 0)
% Complete (Plan) Formula: Child
=IF(IFERROR(IF(AND(TODAY() >= [Start Date (Actual)]@row, TODAY() <= [Finish Date (Actual)]@row), ROUND(NETWORKDAYS([Start Date (Actual)]@row, TODAY()) / [Duration (Actual)]@row, 2), IF(TODAY() > [Finish Date (Actual)]@row, 1, 0)), 0) > 1, 1, IFERROR(IF(AND(TODAY() >= [Start Date (Actual)]@row, TODAY() <= [Finish Date (Actual)]@row), ROUND(NETWORKDAYS([Start Date (Actual)]@row, TODAY()) / [Duration (Actual)]@row, 2), IF(TODAY() > [Finish Date (Actual)]@row, 1, 0)), 0))
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!