Exclude non-productive days from project plan
Hi There. Please advise how can we exclude non-productive day/s from project plan in Smartsheet.
For example. 25th Dec is a non-productive day, then any task with 1day duration should automatically change to next working day.
Answers
-
You can define holidays and non-working days in the Project Settings area of your sheet:
Here's more information: Define Working Days, Non-working Days, and Holidays on a Project Sheet
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
This would work for an activity with duration more than 1d. Please confirm this for an activity with 1d duration. For example, if 26th Nov is a marked as holiday and a task is planned for with 1d duration for 26th Nov, then due date should automatically change to 29th Nov
-
Thank you for clarifying! I don't believe it would automatically shift with 1d, no, but you can see in the Gantt View that these dates will show up as pink.
Please let the Product team know about your request by filling in this form, here.
Thank you!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives