Allow for multiple dependencies?
CeciliaKemi
✭✭
Is it possible to have multiple dependencies in Smartsheet? Ie the start of an activity is dependent on one or another previous activity, which ever finishes last.
Best Answer
-
Yes, let’s say an activity on row 6 is dependent on activities in rows 4 & 5, the predecessor on row 6 would be written as “4, 5”.
Just separate the row numbers with a comma in the predecessor.
Answers
-
Yes, let’s say an activity on row 6 is dependent on activities in rows 4 & 5, the predecessor on row 6 would be written as “4, 5”.