Allow for multiple dependencies?

Options

Is it possible to have multiple dependencies in Smartsheet? Ie the start of an activity is dependent on one or another previous activity, which ever finishes last.

Best Answer

  • Jason Duryea
    Jason Duryea ✭✭✭✭✭✭
    Answer ✓
    Options

    Yes, let’s say an activity on row 6 is dependent on activities in rows 4 & 5, the predecessor on row 6 would be written as “4, 5”.

    Just separate the row numbers with a comma in the predecessor.

Answers

  • Jason Duryea
    Jason Duryea ✭✭✭✭✭✭
    Answer ✓
    Options

    Yes, let’s say an activity on row 6 is dependent on activities in rows 4 & 5, the predecessor on row 6 would be written as “4, 5”.

    Just separate the row numbers with a comma in the predecessor.