  • Jason Duryea
    Jason Duryea ✭✭✭✭✭✭
    Answer ✓

    Yes, let’s say an activity on row 6 is dependent on activities in rows 4 & 5, the predecessor on row 6 would be written as “4, 5”.

    Just separate the row numbers with a comma in the predecessor.