Allow for multiple dependencies?
CeciliaKemi
✭✭
Is it possible to have multiple dependencies in Smartsheet? Ie the start of an activity is dependent on one or another previous activity, which ever finishes last.
Best Answer
-
Yes, let’s say an activity on row 6 is dependent on activities in rows 4 & 5, the predecessor on row 6 would be written as “4, 5”.
Just separate the row numbers with a comma in the predecessor.
Answers
-
Yes, let’s say an activity on row 6 is dependent on activities in rows 4 & 5, the predecessor on row 6 would be written as “4, 5”.
Just separate the row numbers with a comma in the predecessor.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives