Formula IF Statement
I am trying to get the Cleaning Progress to Show "In Progress" when the #Days are greater than 1 but if the Cleaning End Date is populated to return "Complete"
Answers
-
Feel free to change the "Error" into whatever message you want. You need a third option for when the Cleaning End Date is empty and the #Days are less than or equal to one.
=IF([Cleaning End Date]@row = "", IF([#Days]@row > 1, "In Progress", "Error"), "Complete")
-
Thank you, that did work. How would that third option be written? Does it get strung to the existing one you supplied.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.6K Get Help
- 403 Global Discussions
- 215 Industry Talk
- 455 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 56 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!